Kangra News: Situation Has Not Changed In Seven Years, Now How Will The Dharamshala City Become Smart In Four Months?

0

officials say that the ongoing development work for Smart City Dharamshala is difficult to be completed even in the next two years. Neither the Dharamshala city will get its first smart road nor smart street lights are going to be installed till June.

Smart City Dharamshala

Smart City Dharamshala

WhatsApp Channel Join Now
Telegram Group Join Now
Instagram Join Now

Dharamshala: The effort to make the Dharamshala city smart had started in the year 2016, but due to unsmart planning of the officials and slow pace of work, not a single development work has been completed on time. The deadline to complete the ongoing development works in Himachal Pradesh’s first smart city Dharamshala is June 24, 2024. In any case, all development works will have to be completed by the month of June.

On the other hand, officials say that the ongoing development work for Smart City Dharamshala is difficult to be completed even in the next two years. Neither the Dharamshala city will get its first smart road nor smart street lights are going to be installed till June. If the work is not completed within the stipulated time, the central government will decide what to do next. At present, there are more than six works of Smart City Dharamshala which are half-completed.

According to complete information, earlier the deadline to complete all the work of Smart City Dharamshala was till June 2021, but after the work was not completed, its deadline was extended till June 30, 2023. Even after getting additional time of two years, all the work in Dharamshala remains incomplete. Now the Central Government has given the deadline to complete the work by June 24, 2024. But the work is not going to be completed even in this time period.

Dharamshala got the status of Smart City in the year 2016, but even after more than seven years have passed, people have not been able to get even a single smart facility in the city. The people of Dharamshala city have neither got smart roads nor smart street lights. Apart from this, the biggest problem of the city is parking, but in seven years people have not been able to get even a single new parking facility. Only 10 percent development work has been completed of multi-storey parking being built near Dharamshala bus stand.

Apart from this, not a single e-toilet has been installed in the city in seven years. Due to this, people and tourists are forced to defecate in the open. The underground dustbins installed in Dharamshala city have also been removed from there and kept at the dumping site. The people of the merge area of Dharamshala have not been able to get sewerage facility. Apart from this, the work of the corridor from KCC Chowk to Dharamshala Stadium has also not been completed even 10 percent.

How much was spent on smart city works?

  • Underground dustbin: 140 dustbins worth Rs 6.07 crore were installed, which are now being uprooted.
  • Smart Road: The Smart Road to be built worth Rs 18.03 crore is still incomplete, which will not be completed even in the next one year.
  • Smart LED street lights: About 7,000 new smart LED street lights were to be installed in the city at a cost of Rs 25 crore, of which even 50 percent of the work has not been completed.
  • Barrier Free Smart Bus Shelter: The Barrier Free Smart Bus Shelter built at a cost of Rs 9 crore is only a tin box, people are not getting any smart facility there.
  • Dalai Lama Temple Parking: The parking work being built at a cost of Rs 4.86 crore along with the Dalai Lama Temple located in McLeodganj is also incomplete.
  • Root Zone Treatment Naddi: The construction of Root Zone Treatment Plant located at Naddi at a cost of Rs 2.78 crore is stopped due to NOC.
  • Street Vending Zone: The work of street vending zones to be built at various places in Dharamshala city has not started till date.
  • Smart Streets: The interlock tiles laid at various places in the city at a cost of Rs 9 crore have started falling apart within a year or two.

The deadline to complete the ongoing smart city work in Dharamshala city is June 24, 2024, but the work will not be completed on time. Earlier there was delay due to tenders etc. and later due to excessive rain in Dharamshala many works could not be completed. Many smart city works will not be completed till the deadline. After June it will be known what further decision the Central Government takes.

  • Zafar Iqbal, CEO Smart City Dharamshala

Read More: Himachal News: PM Narendra Modi Laid Online Foundation Stone Of Three Critical Care Blocks Of Himachal Pradesh

We’re now on WhatsApp –Click to join

Kumud Sharma

https://diarytimes.com/

Continuing the achievement of the journey of effectiveness and credibility of more than 10 years in the career of journalism, as a woman journalist, I am Serving as the founder, promoter and editor of DiaryTimes with the trust and support of all. My credible coverage may not have given a big shape to the numbers, but my journey presents articles that make you aware of the exact and meaningful situations of Himachal’s politics, ground issues related to the public, business, tourism and the difficult geographical conditions of the state and financial awareness. DiaryTimes, full of the experience of my precise editorial expertise, is awakening the flame of credible journalism among all of you, so that the eternal flame of meaningful change can be lit in the life of the people of the state and the atrocities being committed against the people can be brought to the fore, I am motivated for that. If even a small change comes with the power of my journalism and the whole world becomes a witness to that issues, then I will consider myself fortunate.

Leave a Reply

Your email address will not be published. Required fields are marked *

Google News Titles